Who furnishes (F) and installs (I) each part of the electrical scope, what is not applicable (N/A), by others (BO), or existing (E). Each letter says where it came from: a person, an RFI answer, RRE’s standard (the same on every past proposal), or this job’s takeoff. Rows nobody can fill are asked of the GC from here or from RFIs. The proposal prints these letters.
0 set by a person · 0 from RFI answers · 112 RRE standard · 36 from the takeoff
| Item | Letter | Source | Why | |
|---|---|---|---|---|
| LIGHT FIXTURES | Nobody knows | Who supplies the fixtures is not on the takeoff, so it is left blank: check the fixture schedule. (Owner-furnished on 3 of 5 past jobs.) | ||
| LAMPS | Nobody knows | Who supplies the fixtures is not on the takeoff, so it is left blank: check the fixture schedule. (Owner-furnished on 3 of 5 past jobs.) | ||
| EXIT LTG’S | Nobody knows | Who supplies the fixtures is not on the takeoff, so it is left blank: check the fixture schedule. (Owner-furnished on 3 of 5 past jobs.) | ||
| EMERGENCY LTG’S | Nobody knows | Who supplies the fixtures is not on the takeoff, so it is left blank: check the fixture schedule. (Owner-furnished on 3 of 5 past jobs.) | ||
| TIME CLOCK | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 4 of 5 past jobs: check the drawings. | ||
| LTG CONTACTORS | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 4 of 5 past jobs: check the drawings. | ||
| OVERRIDE SWITCH | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 4 of 5 past jobs: check the drawings. | ||
| LTG CONTROL PANEL (LCP) | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 2 of 5 past jobs: check the drawings. | ||
| POWER PACK / DIMMING RELAY | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 2 of 5 past jobs: check the drawings. |
| Item | Letter | Source | Why | |
|---|---|---|---|---|
| FLOOR BOXES / POWER POLES | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 2 of 5 past jobs: check the drawings. | ||
| POWER TO KITCHEN EQUIPMENT | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 2 of 5 past jobs: check the drawings. | ||
| POWER TO ANSUL / HOOD SYSTEM | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 2 of 5 past jobs: check the drawings. | ||
| CONDUIT RACKS / HANGERS / UNISTRUT SUPPORTS | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 4 of 5 past jobs: check the drawings. | ||
| TELEPHONE TERMINAL BACKBOARD | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 2 of 5 past jobs: check the drawings. | ||
| POWER TO EXHAUST FANS | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 3 of 5 past jobs: check the drawings. | ||
| 120V POWER FOR MODULAR FURNITURE / POS | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 4 of 5 past jobs: check the drawings. | ||
| POWER FOR HAND DRYER | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 2 of 5 past jobs: check the drawings. |
| Item | Letter | Source | Why | |
|---|---|---|---|---|
| 120V POWER TO ELECTRIC WATER HEATER | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 3 of 5 past jobs: check the drawings. | ||
| DISCONNECT SWITCH FOR WATER HEATER & EQUIPMENT CONNECTION | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 3 of 5 past jobs: check the drawings. |
| Item | Letter | Source | Why | |
|---|---|---|---|---|
| PANELBOARDS | Nobody knows | No panels on the takeoff, so it is left blank: check the single line. (RRE marked F+I on 3 of 5 past jobs.) | ||
| BUILDING INTERIOR TRANSFORMER | Nobody knows | No transformer on the takeoff, so it is left blank: check the single line. (Existing on 3 of 5 past jobs.) | ||
| TRANSFORMER BRACKETS - FOR HANGING ETC | Nobody knows | No transformer on the takeoff, so it is left blank: check the single line. (Existing on 3 of 5 past jobs.) | ||
| PANEL BREAKERS | Nobody knows | No panels on the takeoff, so it is left blank: check the single line. (RRE marked F+I on 3 of 5 past jobs.) | ||
| PULL CANS / GUTTERS | Nobody knows | No panels on the takeoff, so it is left blank: check the single line. (RRE marked F+I on 4 of 5 past jobs.) | ||
| PANEL FEEDER CONDUIT PER PLAN | Nobody knows | No panels on the takeoff, so it is left blank: check the single line. (RRE marked F+I on 4 of 5 past jobs.) | ||
| PANEL FEEDER WIRES / CONDUCTORS PER PLAN | Nobody knows | No panels on the takeoff, so it is left blank: check the single line. (RRE marked F+I on 4 of 5 past jobs.) | ||
| ELECTRICAL DISCONNECT PER PLAN | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 4 of 5 past jobs: check the drawings. |
| Item | Letter | Source | Why | |
|---|---|---|---|---|
| RACEWAYS / BACK BOXES FOR CAMERAS | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 3 of 5 past jobs: check the drawings. | ||
| RACEWAYS / BACK BOXES FOR SPEAKERS | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 3 of 5 past jobs: check the drawings. |
| Item | Letter | Source | Why | |
|---|---|---|---|---|
| SERVICE RECEPTACLES / POWER | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 4 of 5 past jobs: check the drawings. | ||
| POWER TO RTU’S / HEATPUMPS | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 2 of 5 past jobs: check the drawings. |