Who furnishes (F) and installs (I) each part of the electrical scope, what is not applicable (N/A), by others (BO), or existing (E). Each letter says where it came from: a person, an RFI answer, RRE’s standard (the same on every past proposal), or this job’s takeoff. Rows nobody can fill are asked of the GC from here or from RFIs. The proposal prints these letters.
0 set by a person · 0 from RFI answers · 109 RRE standard · 43 from the takeoff
| Item | Letter | Source | Why | |
|---|---|---|---|---|
| LIGHT FIXTURES | Nobody knows | Who supplies the fixtures is not on the takeoff, so it is left blank: check the fixture schedule. (Owner-furnished on 3 of 5 past jobs.) | ||
| LAMPS | Nobody knows | Who supplies the fixtures is not on the takeoff, so it is left blank: check the fixture schedule. (Owner-furnished on 3 of 5 past jobs.) | ||
| EXIT LTG’S | Nobody knows | Who supplies the fixtures is not on the takeoff, so it is left blank: check the fixture schedule. (Owner-furnished on 3 of 5 past jobs.) | ||
| EMERGENCY LTG’S | Nobody knows | Who supplies the fixtures is not on the takeoff, so it is left blank: check the fixture schedule. (Owner-furnished on 3 of 5 past jobs.) | ||
| TIME CLOCK | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 4 of 5 past jobs: check the drawings. | ||
| LTG CONTACTORS | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 4 of 5 past jobs: check the drawings. | ||
| OVERRIDE SWITCH | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 4 of 5 past jobs: check the drawings. | ||
| LTG CONTROL PANEL (LCP) | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 2 of 5 past jobs: check the drawings. | ||
| POWER PACK / DIMMING RELAY | From the takeoff a guess: check it | 1 takeoff line, e.g. POWER RECEPTACLE - ENTRY SECURITY (EAS POWER PACK / CAPBOX). |
| Item | Letter | Source | Why | |
|---|---|---|---|---|
| TRENCH & BACKFILL PARKING POLE LTG MAX 2FT DEPTH | Nobody knows | This job's takeoff shows 2 takeoff lines, e.g. LOW VOLTAGE - ENTRY DOOR LOOP TRENCHING & PRE-INSTALL COORDINATION, though RRE marked N/A on all 5 past proposals: left blank to check. |
| Item | Letter | Source | Why | |
|---|---|---|---|---|
| FLOOR BOXES / POWER POLES | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 2 of 5 past jobs: check the drawings. | ||
| POWER TO ANSUL / HOOD SYSTEM | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 2 of 5 past jobs: check the drawings. | ||
| POWER FOR HAND DRYER | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 2 of 5 past jobs: check the drawings. |
| Item | Letter | Source | Why | |
|---|---|---|---|---|
| SERVICE RECEPTACLES / POWER | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 4 of 5 past jobs: check the drawings. | ||
| POWER TO RTU’S / HEATPUMPS | From the takeoff a guess: check it | Not on the takeoff, but RRE carried it on 2 of 5 past jobs: check the drawings. |
| Item | Letter | Source | Why | |
|---|---|---|---|---|
| OFF-HAULING EXCESS SOIL | Nobody knows | This job's takeoff shows 2 takeoff lines, e.g. LOW VOLTAGE - ENTRY DOOR LOOP TRENCHING & PRE-INSTALL COORDINATION, though RRE marked N/A on all 5 past proposals: left blank to check. | ||
| COMPACT ELECTRICAL TRENCHES | Nobody knows | This job's takeoff shows 2 takeoff lines, e.g. LOW VOLTAGE - ENTRY DOOR LOOP TRENCHING & PRE-INSTALL COORDINATION, though RRE marked N/A on all 5 past proposals: left blank to check. |