Checks to see if all required documentation is uploaded and received by RRE.
Per the RRE Bid Intake Guideline →. Only missing panel schedules block. Hover a row for the detail.
| Check | Status | Found | Next step |
|---|---|---|---|
| Job facts stated | warning | 1 blank: area (sq ft). | Type them on Step 1. |
| Electrical drawings | pass | 62 sheets, all legible. | |
| Panel schedules | blocker | None found. | Ask the GC for the panel schedules before pricing gear or feeders. |
| Single-line / riser | not included | Not included in the set. | Ask for the one-line if the job touches service, feeders or gear. |
| Lighting information | pass | 25 fixture lines. | |
| Equipment schedules | pass | 13 equipment connections. | |
| Specifications | pass | On a drawing sheet. | |
| Utility / civil | not checked | No site sheet — fine if interior only. | Confirm whether the job includes site or utility scope. |
| Existing conditions | warning | No demolition read on a TI job. | Ask for the existing-conditions / demolition drawings. |
| Addenda / revisions | not checked | Base set only. | Check the bid portal for the latest revision before submitting. |
| Architectural drawings | pass | 15 A sheets read for electrical scope: A001, A003, A101, A102, A105, A201…. | |
| Responsibility matrix / GC scope | pass | On at Roseville_LL PERMIT BID SET_FULL p.4. |