Each page keeps its own drawing number when the package is reissued, so a later issue can be compared against this one rather than started again.
Wired as: Homeruns in 3/4" EMT with #10; fixtures in MC luminary cable; device drops in MC — set by kelchlin.
The RRE item carries no price for the part named, so the estimate has the install labor and rough-in only, and the vendor or sub prices the rest. Send the lighting and gear lists from Material list & vendor quotes.
| Line | Needs a price for | Count | Sheet |
|---|---|---|---|
LIGHT FIXTURE TYPE N Exitronix 902E recessed wall exit sign 5W (sales), CFCI, unswitched leg (kn 1) | LED GRN EXIT FIXTURE | 1 ea | E2.0 |
LIGHT FIXTURE TYPE EX Exitronix GVEX exit sign w/ 90-min battery (BOH), CFCI, unswitched leg | LED GRN EXIT FIXTURE | 1 ea | E2.0 |
LIGHT FIXTURE TYPE EM Isolite LMIGN-EM ceiling recessed emergency light 6W, CFCI, unswitched leg (kn 1 / gen e) | LED EMERGENCYLIGHT DUAL | 6 ea | E2.0 |
| Line | Needs a price for | Count | Sheet |
|---|---|---|---|
PANELBOARD 100A MCB 120/208V 3PH 4W 42 CIRCUIT SURFACE NEMA 1 10KAIC (PANEL L) New Panel L, 42 circuit positions | 100/28 120/208V PNL 3PH | 1 ea | E4.1 |
| Line | Needs a price for | Count | Sheet |
|---|---|---|---|
TIME CLOCK 24 HR / 7 DAY ASTRONOMICAL (INTERMATIC ET91215CR OR EQUAL) TC1 Controls L-1,3,5,7,9,13,15,17,21 (REM TC) + 3 spares | 208/277V 24HR DPST 40A | 1 ea | E4.0 |
TIME CLOCK SET-UP AND PROGRAMMING - TC1 Intermatic ET91215CR astronomical time clock, 0-2 hr storefront override Set all time clocks per the owner's representative at turnover (AS01 Turnover Requirements 5); thermostats in the same note are the mechanical contractor's. | 208/277V 24HR DPST 40A | 1 ea | A101 |
Read off the schedules and notes. RRE buys none of the material named here. Check each against the responsibility matrix on the proposal: these are what it should say is by others.
| Line | Furnished by | Installed by | RRE’s part | Sheet |
|---|---|---|---|---|
CIRCUIT BREAKER 50A 3-POLE 480V BOLT-ON (PANEL H) Struck by kelchlin: Not in this bid: answered on the drawing instead of a RRE Components item. | — | not stated | Struck: not in this bid | E4.1 |
CIRCUIT BREAKER 20A 1-POLE 277V BOLT-ON (PANEL H SPARES) Struck by kelchlin: Not in this bid: answered on the drawing instead of a RRE Components item. | — | not stated | Struck: not in this bid | E4.1 |
CIRCUIT BREAKER 20A 1-POLE 120V BOLT-ON (PANEL L) Struck by kelchlin: Not in this bid: answered on the drawing instead of a RRE Components item. | — | not stated | Struck: not in this bid | E4.1 |
CIRCUIT BREAKER 15A 3-POLE 208V BOLT-ON (PANEL L, EDH-1) Struck by kelchlin: Not in this bid: answered on the drawing instead of a RRE Components item. | — | not stated | Struck: not in this bid | E4.1 |
BREAKER HANDLE TIE (PANEL L POS COUNTER L-6/8/10/12) Struck by kelchlin: Not in this bid: answered on the drawing instead of a RRE Components item. | — | not stated | Struck: not in this bid | E4.1 |
GROUNDING ELECTRODE CONDUCTOR #6 CU BARE (XFMR SEPARATELY DERIVED SYSTEM) Struck by kelchlin: Not in this bid: answered on the drawing instead of a RRE Components item. |
Symbols on this set. No symbol library was found on the drawings, and no engineering firm was identified from the title blocks, so there is no conventions file to fall back on either. This set is read against the default library alone: NECA 100-2006. It is the firm's baseline for what a symbol MEANS where a legend is silent, ambiguous or absent, and it is also the checklist of which symbol categories a plan of this kind ought to show. A line named from the baseline rather than from a legend is named by convention, not by the set. It is reported as 'named from NECA 100, confirm' and carries a semantic-risk flag — a misread convention is a 3× error that no percentage band expresses.
| Drawing | Title | What is waiting | Review | |
|---|---|---|---|---|
A101 page 16 | CONSTRUCTION FLOOR PLAN | Read. | ✓ confirmed by kelchlin · Sep 29, 11:52 PM | Open to reopen or edit → |
E1.0 page 39 | ELECTRICAL LEGENDS & SCHEDULES scale not set | Read. Confirmed with 1 question still open; the Takeoff lists it. | ✓ confirmed by kelchlin · Sep 29, 11:53 PM | Open to reopen or edit → |
E1.0 page 39 | ELECTRICAL LEGENDS & SCHEDULES scale not set | Read. Confirmed with 1 question still open; the Takeoff lists it. | ✓ confirmed by kelchlin · Sep 29, 11:53 PM | Open to reopen or edit → |
E2.0 page 40 | LIGHTING PLAN | Read. Confirmed with 2 questions still open; the Takeoff lists them. | ✓ confirmed by kelchlin · Sep 29, 11:57 PM | Open to reopen or edit → |
E2.0 page 40 | LIGHTING PLAN | Read. Confirmed with 2 questions still open; the Takeoff lists them. | ✓ confirmed by kelchlin · Sep 29, 11:57 PM | Open to reopen or edit → |
| Drawing | Title | What is waiting | Review | |
|---|---|---|---|---|
A001 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 4 | SCHEDULES & DETAILS | Read for scope: nothing electrical on it. | nothing open | See the page → |
A003 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 9 | EGRESS PLAN | Read for scope: nothing electrical on it. | nothing open | See the page → |
A102 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 17 | CONSTRUCTION RCP | Read for scope: 1 line taken off. | nothing open | See the page → |
A102 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 17 | CONSTRUCTION RCP | Read for scope: 1 line taken off. | nothing open | See the page → |
A105 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 20 | FIXTURE PLAN | Read for scope: nothing electrical on it. | nothing open | See the page → |
A201 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 21 |
| Drawing | Title | What is waiting | Review | |
|---|---|---|---|---|
rocklinelectric.net Mail Fwd INVITATION p1 rocklinelectric.net Mail - Fwd_ INVITATION TO BID - Intimissimi - Roseville CA.pdf · page 1 | Invitation to Bid email (page 1) | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (001-rocklinelectric.net Mail - Fwd_ INVITATION TO BID - Intimissimi - Roseville CA.pdf, page 1): Forwarded ITB email from David Nice Builders, header/signature only. | not read | Open the page → |
rocklinelectric.net Mail Fwd INVITATION p2 rocklinelectric.net Mail - Fwd_ INVITATION TO BID - Intimissimi - Roseville CA.pdf · page 2 | Invitation to Bid email (page 2) | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (001-rocklinelectric.net Mail - Fwd_ INVITATION TO BID - Intimissimi - Roseville CA.pdf, page 2): Bid info: Intimissimi Roseville, due 2/3/25 3PM EST, interior build-out, schedule 4/7-6/6/25. | not read | Open the page → |
rocklinelectric.net Mail Fwd INVITATION p3 rocklinelectric.net Mail - Fwd_ INVITATION TO BID - Intimissimi - Roseville CA.pdf · page 3 | Invitation to Bid email (page 3) | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (001-rocklinelectric.net Mail - Fwd_ INVITATION TO BID - Intimissimi - Roseville CA.pdf, page 3): Trade invited: 16000 Electrical; contacts and PipelineSuite login; no drawing work. | not read | Open the page → |
A000 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 1 |
| — |
| not stated |
| Struck: not in this bid |
| E4.0 |
TIE-IN AT EXISTING LANDLORD SWITCHBOARD 100A CB (EXISTING BREAKER, NO NEW GEAR) Struck by kelchlin: Not in this bid: answered on the drawing instead of a RRE Components item. | — | not stated | Struck: not in this bid | E4.0 |
SAFE-OFF EXISTING ELECTRICAL (TI) RRE carries the line; the read says “removal is by others”. | Others | not stated | RRE carries it; a part is by others | A101 |
TEMPORARY POWER AND LIGHTING FOR CONSTRUCTION Struck by House rule (RRE lead estimator practice): Not in this bid: RRE’s lead estimator carries no temporary power (none on his last three estimates, and on earlier ones none even where the specs gave it to the EC). Put it back if this job needs it. | — | not stated | Struck: not in this bid | E5.0 |
LIGHT FIXTURE TYPE T The drawings say “owner furnished”. | Owner | not stated | RRE installs / connects only | E2.0 |
LIGHT FIXTURE TYPE A The drawings say “owner furnished”. | Owner | not stated | RRE installs / connects only | E2.0 |
TRACK, 3-CIRCUIT 120V SURFACE (Quattrobi XTS) Struck by kelchlin: Not in this bid: answered on the drawing instead of a RRE Components item. | Owner | not stated | Struck: not in this bid | E2.0 |
DOUBLE DUPLEX (QUAD) RECEPTACLE 20A The drawings say “by gc”. | GC | not stated | RRE installs / connects only | E3.0 |
DATA OUTLET POSITION, WALL (video wall +85" AFF, storefront) The drawings say “by gc”. | GC | not stated | RRE installs / connects only | E3.0 |
#6 BARE CU GROUNDING ELECTRODE CONDUCTOR - 30 KVA XFMR (SEPARATELY DERIVED) Struck by kelchlin: Not in this bid: answered on the drawing instead of a RRE Components item. | — | not stated | Struck: not in this bid | E4.0 |
CIRCUIT BREAKER 50A 3P 480V BOLT-ON, 22 KAIC (PANEL H) Struck by kelchlin: Not in this bid: answered on the drawing instead of a RRE Components item. | — | not stated | Struck: not in this bid | E4.1 |
CIRCUIT BREAKER 20A 1P 277V BOLT-ON, 22 KAIC (PANEL H, SPARE) Struck by kelchlin: Not in this bid: answered on the drawing instead of a RRE Components item. | — | not stated | Struck: not in this bid | E4.1 |
CIRCUIT BREAKER 20A 1P 120/208V BOLT-ON, 10 KAIC (PANEL L) Struck by kelchlin: Not in this bid: answered on the drawing instead of a RRE Components item. | — | not stated | Struck: not in this bid | E4.1 |
CIRCUIT BREAKER 15A 3P 208V BOLT-ON, 10 KAIC (PANEL L, EDH-1) Struck by kelchlin: Not in this bid: answered on the drawing instead of a RRE Components item. | — | not stated | Struck: not in this bid | E4.1 |
BREAKER HANDLE TIE, 1P BOLT-ON (PANEL L POS COUNTER CKTS 6,8,10,12) Struck by kelchlin: Not in this bid: answered on the drawing instead of a RRE Components item. | — | not stated | Struck: not in this bid | E4.1 |
TEMPORARY POWER AND LIGHTING FOR CONSTRUCTION (EC scope, spec 5.1g) Struck by House rule (RRE lead estimator practice): Not in this bid: RRE’s lead estimator carries no temporary power (none on his last three estimates, and on earlier ones none even where the specs gave it to the EC). Put it back if this job needs it. | — | not stated | Struck: not in this bid | E5.0 |
1-1/2" CONDUIT IN SLAB TRENCH, (7) RUNS, BOH WALL TO CASH DESK STUB-UP (horizontal in-slab run only) The drawings say “by gc”. | GC | not stated | RRE installs / connects only | A101 |
LIGHT FIXTURE AIMING / DIRECTIONAL ADJUSTMENT, TRACK SPOTLIGHT TYPE T (KR103) AND RECESSED TYPE A (SLDRT), AS DIRECTED BY OWNER PM The drawings say “by owner”. | Owner | not stated | RRE installs / connects only | A101 |
LED STRIP LIGHT, WARM WHITE, CONCEALED AROUND OVAL MIRROR PERIMETER (OM detail) The drawings say “owner-furnished”. | Owner | not stated | RRE installs / connects only | A213 |
TEMPORARY POWER AND LIGHTING FOR CONSTRUCTION - tenant space #111, 1231 sf, from new Panel L / LL source Struck by House rule (RRE lead estimator practice): Not in this bid: RRE’s lead estimator carries no temporary power (none on his last three estimates, and on earlier ones none even where the specs gave it to the EC). Put it back if this job needs it. | — | not stated | Struck: not in this bid | A101 |
EQUIPMENT CONNECTION - VAV-1 Titus AESV VAV box, 120V 1-phase, factory control transformer and power fuse, above ceiling Struck by kelchlin: Not in this bid: answered on the drawing instead of a RRE Components item. | — | not stated | Struck: not in this bid | A101 |
16/2 CMR 0-10V DIMMING CABLE (TYPE B / BE 2x2 LED PANEL, LITHONIA CPX ...ZT 0-10V DRIVER), IN LIGHTING EMT Struck by kelchlin: Not in this bid: answered on the drawing instead of a RRE Components item. | — | not stated | Struck: not in this bid | E1.0 |
E3.0 page 41 |
POWER PLAN |
| Read. Confirmed with 3 questions still open; the Takeoff lists them. |
| ✓ confirmed by kelchlin · Sep 29, 11:58 PM |
| Open to reopen or edit → |
E3.0 page 41 | POWER PLAN | Read. Confirmed with 3 questions still open; the Takeoff lists them. | ✓ confirmed by kelchlin · Sep 29, 11:58 PM | Open to reopen or edit → |
E4.0 page 42 | RISER DIAGRAM scale not set | Read. Confirmed with 3 questions still open; the Takeoff lists them. | ✓ confirmed by kelchlin · Sep 30, 1:57 PM | Open to reopen or edit → |
E4.0 page 42 | RISER DIAGRAM / SWITCHBANK DETAIL / LIGHTING CONTROL DIAGRAM scale not set | Read. Confirmed with 3 questions still open; the Takeoff lists them. | ✓ confirmed by kelchlin · Sep 30, 1:57 PM | Open to reopen or edit → |
E5.0 page 44 | ELECTRICAL SPECIFICATIONS scale not set | Read. Confirmed with 1 question still open; the Takeoff lists it. | ✓ confirmed by kelchlin · Sep 30, 12:01 AM | Open to reopen or edit → |
E5.0 page 44 | ELECTRICAL SPECIFICATIONS scale not set | Read. Confirmed with 1 question still open; the Takeoff lists it. | ✓ confirmed by kelchlin · Sep 30, 12:01 AM | Open to reopen or edit → |
E6.0 page 45 | ELECTRICAL ENERGY FORMS scale not set | Read. | ✓ confirmed by kelchlin · Sep 30, 12:02 AM | Open to reopen or edit → |
E6.0 page 45 | ELECTRICAL ENERGY FORMS scale not set | Read. | ✓ confirmed by kelchlin · Sep 30, 12:02 AM | Open to reopen or edit → |
CROSS SECTION |
| Read for scope: nothing electrical on it. |
| nothing open |
| See the page → |
A202 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 22 | CROSS SECTION | Read for scope: nothing electrical on it. | nothing open | See the page → |
A204 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 24 | VESTIBULE AND BOH ELEVATION | Read for scope: nothing electrical on it. | nothing open | See the page → |
A211 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 25 | CONSTRUCTION DETAILS | Read for scope: nothing electrical on it. | nothing open | See the page → |
A213 page 27 | CONSTRUCTION DETAILS | Read. | nothing open | Read it → |
A301 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 28 | STOREFRONT ELEVATION | Read for scope: nothing electrical on it. | nothing open | See the page → |
A302 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 29 | STOREFRONT DETAILS | Read for scope: nothing electrical on it. | nothing open | See the page → |
A303 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 30 | STOREFRONT DETAILS | Read for scope: nothing electrical on it. | nothing open | See the page → |
A401 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 32 | FRAMING & MISC. DETAILS | Read for scope: 2 lines taken off. | nothing open | See the page → |
A402 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 33 | PARTITION TYPES | Read for scope: nothing electrical on it. | nothing open | See the page → |
AS01 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 2 | SPECIFICATIONS | Read for scope: 2 lines taken off. | nothing open | See the page → |
D102 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 11 | DEMOLITION RCP | Read for scope: 1 line taken off. | nothing open | See the page → |
D102 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 11 | DEMOLITION RCP | Read for scope: 1 line taken off. | nothing open | See the page → |
E4.1 page 43 | PANEL SCHEDULES scale not set | Read. | nothing open | Read it → |
E4.1 page 43 | PANEL SCHEDULES scale not set | Read. | nothing open | Read it → |
M1.0 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 34 | MECHANICAL LEGENDS, NOTES, AND SCHEDULES | Read for scope: 1 line taken off. | nothing open | See the page → |
M2.0 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 35 | MECHANICAL FLOOR PLAN | Read for scope: nothing electrical on it. | nothing open | See the page → |
M4.0 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 37 | MECHANICAL SPECIFICATIONS | Read for scope: nothing electrical on it. | nothing open | See the page → |
S301 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 48 | SECTIONS & DETAILS | Read for scope: nothing electrical on it. | nothing open | See the page → |
ST1 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 50 | STRUCTURAL DETAILS | Read for scope: 1 line taken off. | nothing open | See the page → |
COVER SHEET |
| Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 1): Cover sheet: project data, directory, drawing index only. |
| not read |
| Open the page → |
A002 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 5 | ACCESSIBILITY DIAGRAMS | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 5): ADA clearance diagrams, no electrical work. | not read | Open the page → |
A002.1 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 6 | ACCESSIBILITY DIAGRAMS | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 6): ADA counters, reach ranges and signage diagrams (non-illuminated); no electrical. | not read | Open the page → |
A002.2 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 7 | MALL MAP | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 7): Mall key map only. | not read | Open the page → |
A002.3 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 8 | SITE PLAN | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 8): Site/parking plan only. | not read | Open the page → |
A103 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 18 | FLOOR FINISH PLAN | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 18): Floor finishes and schedule; storefront footboard cable flap also shown on A105. | not read | Open the page → |
A104 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 19 | WALL FINISH PLAN | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 19): Wall finishes and schedule only. | not read | Open the page → |
A203 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 23 | ADA FITTING ROOM ELEVATION | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 23): Fitting room mirrors, hooks, bench, curtain; checked at zoom, no devices or fixtures. | not read | Open the page → |
A212 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 26 | Construction Details | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 26): Fitting-room portals, BOH door frame and floor transition details; checked at zoom, no devices or supports. | not read | Open the page → |
A304 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 31 | Storefront Details | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 31): Storefront plan sections (studs, glazing, folding panels); checked at zoom, no sign power or J-boxes. | not read | Open the page → |
AS02 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 3 | SPECIFICATIONS | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 3): Architectural general specs; electrical section only refers to E drawings. | not read | Open the page → |
D101 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 10 | DEMOLITION FLOOR PLAN | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 10): Demolition plan - RRE does not bid demolition. | not read | Open the page → |
D103 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 12 | DEMOLITION CROSS SECTION | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 12): Demolition section - RRE does not bid demolition. | not read | Open the page → |
D104 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 13 | DEMOLITION CROSS SECTION | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 13): Demolition section - RRE does not bid demolition. | not read | Open the page → |
D105 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 14 | DEMOLITION CROSS SECTION | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 14): Demolition section - RRE does not bid demolition. | not read | Open the page → |
D106 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 15 | DEMOLITION STOREFRONT ELEVATION | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 15): Demolition storefront elevations - RRE does not bid demolition. | not read | Open the page → |
M3.0 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 36 | Mechanical Details | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 36): Duct, damper, diffuser and hanger details only. | not read | Open the page → |
M5.0 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 38 | Mechanical Energy Forms | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 38): Title 24 mechanical compliance forms. | not read | Open the page → |
S101 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 46 | Partial 1st Fl. Framing Plan | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 46): Structural wall framing plan, walls and grid only. | not read | Open the page → |
S201 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 47 | RCP Framing Plan | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 47): Structural ceiling framing with seismic bracing and hanger wires; no fixtures or devices. | not read | Open the page → |
ST0 Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf · page 49 | General Notes | Looked at by the takeoff and not read: no electrical work on it. The sorter looked at the page (000-Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf, page 49): Structural general notes, abbreviations, design loads. | not read | Open the page → |