Who furnishes (F) and installs (I) each part of the electrical scope, what is not applicable (N/A), by others (BO), or existing (E). Each letter says where it came from: a person, an RFI answer, RRE’s standard (the same on every past proposal), or this job’s takeoff. Rows nobody can fill are asked of the GC from here or from RFIs. The proposal prints these letters.
26 set by a person · 0 from RFI answers · 99 RRE standard · 27 from the takeoff
Exterior — light works
Item
Letter
Source
Why
TRENCH & BACKFILL PARKING POLE LTG MAX 2FT DEPTH
Nobody knows
This job's takeoff shows 1 takeoff line, e.g. TRENCH AND BACKFILL, UNDERGROUND CONDUIT (24" MIN COVER), though RRE marked N/A on all 5 past proposals: left blank to check.
Single line works
Item
Letter
Source
Why
CONCRETE PAD FOR GEAR / EQUIP
Nobody knows
This job's takeoff shows 2 takeoff lines, e.g. JUNCTION BOX 6"x6" WEATHERPROOF NEMA 3R, PAD-MOUNTED STUB-UP ON RAISED CONCRETE PAD, POWER FOR RELOCATED (E) VACUUM EQUIPMENT, though RRE marked N/A on all 5 past proposals: left blank to check.
Low voltage works
Item
Letter
Source
Why
HVAC CONTROL WIRING
Nobody knows
This job's takeoff shows 1 takeoff line, e.g. JUNCTION BOX 4" SQUARE WITH SINGLE-GANG RING, THERMOSTAT, though RRE marked N/A on all 5 past proposals: left blank to check.
Underground excavation works
Item
Letter
Source
Why
EV CHARGER
Nobody knows
This job's takeoff shows 10 takeoff lines, e.g. 1" LIQUIDTIGHT FLEXIBLE METAL CONDUIT WHIP WITH CONNECTORS (EVSE CONNECTION), though RRE marked N/A on all 5 past proposals: left blank to check.
SECONDARY FEEDERS
Nobody knows
This job's takeoff shows 4 takeoff lines, e.g. 2" PVC SCH 40 CONDUIT UNDERGROUND (MSB TO PANEL H FEEDER), though RRE marked N/A on all 5 past proposals: left blank to check.
OFF-HAULING EXCESS SOIL
Nobody knows
This job's takeoff shows 1 takeoff line, e.g. TRENCH AND BACKFILL, UNDERGROUND CONDUIT (24" MIN COVER), though RRE marked N/A on all 5 past proposals: left blank to check.
COMPACT ELECTRICAL TRENCHES
Nobody knows
This job's takeoff shows 1 takeoff line, e.g. TRENCH AND BACKFILL, UNDERGROUND CONDUIT (24" MIN COVER), though RRE marked N/A on all 5 past proposals: left blank to check.