What the takeoff said: Read from 000-Copy of Drawings.pdf, page 7. Text is outlined to curves (only a few words in the text layer); read from renders at 60-200 dpi. No responsibility matrix, no equipment schedule, no LV/support details on this sheet. No lines written: every electrical item on SD1 is either existing ((E) site lights, (E) conc light pedestals, (E) electric utility vault, (E) PG&E transformer, (E) power poles/overhead lines) or new work the E set already takes off (E1.1/E5.0: 'NEW ELEC. MAIN SWITCHBOARD CABINET, SEE ELEC. DWGS.', EV chargers EV-1..EV-3).