| PROJECT / BID DETAILS [DIVISON 26 00 00 ] | |
|---|---|
| Bid Submission # | [Bid Submission # — not answered] |
| Drawing Reference & Specs | Copy of 2024.11.28_INT_US_CA_Roseville_Galleria at Roseville_LL PERMIT BID SET_FULL.pdf |
| Addendum Acknowledged | N/A |
| Bid RFI | N/A |
| Labor Requirement | Private / Non-PW |
| Visited Site / Job Walk | [Visited Site / Job Walk — not answered] |
| Projected Start Date | TBD |
| Projected Completion | TBD |
| Project Performance Bond | [Project Performance Bond — not answered] |
| Work Schedule | Normal Working Hours |
| Type of Construction | Tenant Improvement |
| Project Area | [Project Area — not answered] |
| Bid Valid through | 12/06/2026 (60 Days) |
Prepared By: Name:kelchlin (Estimator) Email:[email — not answered] Phone:[phone — not answered] | |


| From | RRE Inc Electrical Contractor |
|---|---|
| Date | 10/07/2026 |
| To | intermissinni-2 115 Galleria Blvd. Roseville CA 95678 |
| COST# | DESCRIPTION | COST FOR DAYWORKS |
|---|---|---|
| BASE BID | Electrical work specifically included per Scope of Work, plans, specifications, qualifications and exclusions. This work will be done during regular hours. | $30,546.06 |
| COST | BASE BID (Alternatives Not Included) | $30,546.06 |


No alternates on this proposal.
| RESPONSIBILITY MATRIX | ||
|---|---|---|
| EQUIPMENT/SCOPE | PROVIDER | REMARKS |
| Lighting Fixtures | ? | |
| Lighting Controls | By Others | Install by RRE |
| Exit / Emergency Lighting | ? | |
| Main Switchboard / Switchgear | By RRE | |
| Panelboards | By RRE | |
| Transformers | By RRE | |
| Primary Utility | By Others | |
| Secondary Utility | By Others | |
| Mechanical / Plumbing Power | ? | |
| Rooftop Equipment Power | By RRE | |
| Signage Power | By RRE | |
| Fire Alarm | N/A | |
| Low Voltage / Data | By RRE | |
| Security / Access / Controls | N/A | |
| Underground Raceway / Feeders | N/A | |

| RESPONSIBILITY MATRIX | ||
|---|---|---|
| EQUIPMENT/SCOPE | PROVIDER | REMARKS |
| Site / Pole Lighting | N/A | |
| EV Charger Infrastructure | N/A | |
| Trenching / Backfill | ? | |
| Concrete / Core Drill / Patchback | ? | |
| Electrical Demo / Safe-Off | By RRE | |
| Temporary Power / Lighting | N/A | |
| Testing / Commissioning | By RRE | |
| Permits / Closeout | By RRE | |
| Site / Parking Lot Lighting | N/A | |
| Pole Bases | N/A | |
| Underground Raceway | N/A | |
| Site Lighting Branch Circuits | N/A | |
| Transformer Pad | By Others | |
| Pull Boxes / Handholes | N/A | |
| Site Signage Power | N/A | |
| Trenching / Excavation | ? | |
| Backfill Material | N/A | |
| Trench Compaction | ? | |
| Compaction Testing | N/A | |
| Concrete / Asphalt Cutting | N/A | |
| Concrete / Asphalt Patchback | N/A | |

| RESPONSIBILITY MATRIX | ||
|---|---|---|
| EQUIPMENT/SCOPE | PROVIDER | REMARKS |
| Excess Soil / Off-Haul | ? | |
| Traffic Control | By Others | |
| Joint Trench | N/A | |
| Note: Project-specific Base Bid Inclusions, Exclusions, and accepted Alternates shall govern in the event of a conflict. | ||


RRE Inc. Electrical Contractors shall not be held liable for any delays in the delivery of electrical gear, equipment, or materials caused by manufacturers, suppliers, shipping carriers, or other third parties beyond our control. This includes, but is not limited to, production backlogs, material shortages, shipping or freight disruptions, or other supply chain issues. In such cases, all project schedules, milestones, and completion deadlines shall be extended on a day-for-day basis equal to the length of the delay. No liquidated damages, penalties, or back charges shall be applied to RRE Inc. Electrical Contractors as a result of such delays. Furthermore, RRE Inc. reserves the right to submit for approval equivalent or substitute materials or to resequence work in a commercially reasonable manner to minimize the impact of such delays.
By approving this submittal, the Owner, Engineer, and/or General Contractor acknowledge that RRE Inc. Electrical Contractors is not responsible for verifying whether the submitted equipment or materials fully align with the electrical design intent. If the approved submittals do not conform to the original design concept or performance criteria, RRE Inc. shall be held harmless from any resulting issues, defects, or performance deficiencies in the electrical system.
All lead times provided are Estimated Ship Dates (ESDs) and are based on information available at the time of issuance. These dates are subject to change without notice due to factors beyond the control of RRE Inc. Electrical Contractors, including but not limited to supplier or manufacturer production schedules, raw material availability, and shipping logistics. RRE Inc. makes no guarantees regarding actual ship or delivery dates and shall not be held liable for any impacts resulting from changes to the ESD.

Payments shall be made each thirty days as the work progresses. The entire amount of the contract shall be paid within thirty days after completion.
Service and Finance Charges are applicable on past accounts at the rate of 1 ½ percent per month on amounts thirty (30) days past due, which is equal to an annual percentage rate of 18 percent. Such charges are shown as “service charges”. There is no service charge if accounts are paid within thirty days of the end of the month in which purchases are made.
Any alteration or deviation from the above specifications involving the extra cost of material and/or labor will only be executed upon written orders for the same and will become an extra charge over the sum mentioned in this contract. All agreements must be made in writing.
The contractor agrees to carry Workman’s Compensation and Public Liability Insurance and also to pay all Sales Taxes, Old Age Benefits, and Unemployment Compensation Taxes upon the material and labor furnished under this contract, as required by the United States Government and the State in which this work is performed.
Respectfully submitted,
Note: This proposal may be withdrawn by us if not accepted within 60 days of the proposal date.
You are hereby authorized to furnish all materials and labor required to complete the work mentioned in the above proposal, for which the undersigned agrees to pay the amount mentioned in the said proposal, and according to the terms thereof. I also agree to pay all reasonable costs, charges, and attorney’s fees that may accrue hereon after any default in payments.
115 Galleria Blvd. Roseville CA 95678 · Bid 2026-09-29
| E1.0 | ELECTRICAL LEGENDS & SCHEDULES |
| E1.0 | ELECTRICAL LEGENDS & SCHEDULES |
| E2.0 | LIGHTING PLAN |
| E2.0 | LIGHTING PLAN |
| E3.0 | POWER PLAN |
| E3.0 | POWER PLAN |
| E4.0 | RISER DIAGRAM |
| E4.0 | RISER DIAGRAM / SWITCHBANK DETAIL / LIGHTING CONTROL DIAGRAM |
| E4.1 | PANEL SCHEDULES |
| E4.1 | PANEL SCHEDULES |
| E5.0 | ELECTRICAL SPECIFICATIONS |
| E5.0 | ELECTRICAL SPECIFICATIONS |
| E6.0 | ELECTRICAL ENERGY FORMS |
| E6.0 | ELECTRICAL ENERGY FORMS |
| A001 | SCHEDULES & DETAILS |
| A003 | EGRESS PLAN |
| A101 | CONSTRUCTION FLOOR PLAN |
| A102 | CONSTRUCTION RCP |
| A102 | CONSTRUCTION RCP |
| A105 | FIXTURE PLAN |
| A201 | CROSS SECTION |
| A202 | CROSS SECTION |
| A204 | VESTIBULE AND BOH ELEVATION |
| A211 | CONSTRUCTION DETAILS |
| A213 | CONSTRUCTION DETAILS |
| A301 | STOREFRONT ELEVATION |
| A302 |
| STOREFRONT DETAILS |
| A303 | STOREFRONT DETAILS |
| A401 | FRAMING & MISC. DETAILS |
| A402 | PARTITION TYPES |
| AS01 | SPECIFICATIONS |
| M1.0 | MECHANICAL LEGENDS, NOTES, AND SCHEDULES |
| M2.0 | MECHANICAL FLOOR PLAN |
| M4.0 | MECHANICAL SPECIFICATIONS |
| S301 | SECTIONS & DETAILS |
| ST1 | STRUCTURAL DETAILS |
| D102 | DEMOLITION RCP |
| D102 | DEMOLITION RCP |
No symbol legend was found on the drawings; symbols were named against NECA 100-2006.
Every scope line cites the sheet the number was read from, taken straight from the model’s provenance rather than reconstructed by hand. Back to the estimate →